Construction Timescale

Print

The future timescales for the project are dependent on how long it takes to obtain planning permission for the new Havant Thicket Winter Storage Reservoir. A provisional timescale is set out in the table below. Please note that the timescales are likely to be subject to change.

                                    
Activity
Date
Early preparatory work
Habitat creation, enhancement and species relocation
Removal of trees where necessary
Diversion of paths and bridleway
Year 1 & 2
Site preparation work
Construction of access road and site compound
Fencing off the construction area
Stripping and storing soil
Year 3 & 4
Main construction phase
Drainage works
Excavation of clay
Embankment construction
Creation of path networks
Year 5 to 8
Filling and commissioning
Water pumped up from the springs
Construction of ancillary amenities
Year 9 & 10
       