Timescale

Print

The key dates of the project are displayed below. Green = Task complete; Orange = Task underway; Red = Not yet started

Activity

Date

Public Consultation exercise

Initial consultation: briefing for East Hants District Council, Havant Borough Council & Horndean Parish Council

February 2008

Letter to residents in Leigh Park, Rowlands Castle & Horndean

February 2008

Public exhibitions at Leigh Park, Rowlands Castle & Horndean

8 - 18 March 2008

Posters placed at site advertising proposal and website

Beginning of March 2008

Workshop of interested parties and community groups

29 March 2008

Collation of community feedback

April & May 2008

Stakeholder meeting

23 May 2008

Publication of Newsletter

30 September 2008

Publication of results of consultation

30 October 2008

Stakeholder meeting

5 December 2008

 

 

Environmental Impact Assessment

Additional bat surveys

April 2008 to February 2009

Additional summer bat surveys

April to August 2009

Additional bird surveys

June 2008

Additional winter bird surveys on site

December 2008 to February 2009

National Vegetation Classification (NVC) Survey

Spring 2009

Traffic surveys

July and August 2008

River Habitat and geomorphology surveys

July & October 2008

Invertebrate surveys

July & October 2008

Extended Phase I Habitat Surveys

August & September 2008

Submit request for scoping & submit scoping report

End of February 2009

Eco-subgroup meeting

TBC

Design freeze for EIA

TBC

 

 

Planning application

 

Meeting with planners - pre EIA scoping

Mid- August 2008

Meeting with Local Authority (HBC & EHDC) Planners

April 2009

Meeting with Havant Development Forum

Delayed

Meeting with East Hants Development Forum

Delayed

 

Submit planning application

Delayed 
 

Note: The planning application can not be submitted until the Company has finalised its Water Resources Management Plan (WRMP). In September 2010 a Public Consultation on the plan commenced, the deadline for provision of comments was 26 November 2010. The Company considered the responses and submitted a revised plan to DEFRA on 16 March 2011. For further information click here.

 

Please note that all dates are tentative and liable to change as new information from environmental site studies becomes available

 

 

 

Legal Notice | Site Map

Copyright © Portsmouth Water Ltd
P.O. Box 8,West Street, Havant, Hampshire, PO9 1LG
Registered in England No 2536455 VAT No GB 615375835